Peoria County Farm Bureau Building Update III
Construction on our new office and event space continues to make exciting progress! Over the past several weeks, the site has really started to take shape. The foundation area has been leveled and prepared, and crews have completed the placement of the footings that will support the building's framework.
The next major milestone will be pouring the concrete floor in the event space. Before the concrete is poured, the piping for the in-floor heating system will be installed, providing an energy-efficient way to keep the space comfortable.
Construction will continue after the floor has been poured with the building's framework, and we will soon begin to see the walls go up. This is one of the most exciting phases of the project, as the vision for our new office and event space will become visible.
We appreciate everyone's patience and support as this project moves forward. Be sure to check Facebook and the Blog section on our website for a quick update each week.